Natural Gas / Fuel Oil

Rohm & Haas

82,800 PPH Natural Gas and #6 Fuel Oil Steam Facility

Rohm & Haas

Philadelphia, Pennsylvania

January 1996

ESI supplied the engineering, design, and construction management for the installation of two 1,200 HP Johnston firetube boilers along with all waterside auxiliaries including a duplex sodium zeolite softener and a deaerator with boiler feedwater pumps and two river water booster pumps in a new pre-engineered metal building. Additionally, a back pressure steam turbine was installed as a retrofit to the project to replace an existing pressure reducing valve and generate a small amount of electricity.