Instrumentation and Controls
Bailey Controls
400,000 PPH Natural Gas Utility System Control Modernization
Owner: Bailey Controls, Department of Energy, Rocky Flats Facility
Project Location: Denver, Colorado
Project Completion: December 1995
Project Description:
ESI was commissioned by Bailey Controls to design and project manage the installation of a Bailey INFI-90 system on a 400,000 pph, 250 psig steam facility. This system included four (4) 100,000 pph boilers and all utility plant auxiliaries including two deaerators, two oil storage tank systems, cooling towers, and air compressors.