Environmental Compliance
Department of Energy – Savannah River Facility
Environmental Compliance – Engineering for 20 MW Biomass Plant
Owner: Ameresco Federal Solutions
Project Location: Aiken, South Carolina
Project Completion: December 2011
Project Description:
ESI is performing the engineering for the complete new installation of a bubbling fluidized bed boiler system firing biomass and tire-derived fuel, to make both power and process steam available to the Department of Energy Savannah River Facility. The project includes installation of two bubbling fluidized bed boilers and a nominal 20 MW steam turbine generator.
The air quality control system includes SNCR and precipitator with continuous emissions monitoring system.