Engineering Study & Feasibility Analysis
U. S. Alliance Steam Facility
Environmental Compliance
Owner: U. S. Alliance
Project Location: Coosa Pines, Alabama
Project Completion: June 2001
Project Description:
ESI performed a study for this facility in which various options were considered to bring the existing pulverized coal-fired boilers into upcoming EPA NOx regulation compliance. The study included an economic and technical analysis of all viable NOx reduction systems including: low NOx burners, NOx ports, selective non-catalytic reduction and selective catalytic reduction, as well as a recommended path forward.